The project calendar for the 2027 reporting season

Written by Jessi | August 2026
Home Blog The project calendar for the 2027 reporting season

Financial communications · 8 min read

Annual and sustainability reports: the project calendar for the 2027 season

What the translation actually depends on: the embargo, the number of correction rounds, and terminology that holds up across the management report and the sustainability section. With the calendar from November to April.

A bar chart with five phases: terminology in November, settled chapters from December to January, figures in February, revision from February to March, and approval and layout from March to April. From the figures onwards the whole project runs under embargo, and publication marks the end. Project calendar, 2027 reporting season Example for publication in early April Embargo Nov Dec Jan Feb Mar Apr Terminology Settled chapters Figures Revision Approval and layout Publication Two correction rounds are built into the plan How the five phases relate to each other. From the figures onwards the team works under embargo.

In brief

  • The project calendar runs from November to April, with terminology at the start and galley proof correction at the end.
  • The embargo determines the staffing: a named group of people that cannot be widened at short notice once the figures arrive.
  • Two correction rounds is the realistic planning figure. Each additional round costs three to five working days per language.
  • The management report and the sustainability section need one shared term list, because both are read and audited side by side.

Most companies award the translation of their annual report in the autumn. Why that is, and which three causes account for most of the lost time in spring, is covered in Why the decision is made in September. This article is about delivery: the calendar, the staffing and the terminology work between the two parts of the report.

The calendar from November to April

The plan below assumes publication in early April and English as the required version. It shifts as a whole if your date is earlier or later. What matters is the order, not the exact dates.

Period Phase Output Your decision
November Terminology and translation memory agreed term list, existing material prepared settle the contested terms
December to January Settled chapters foreword, strategy, segments and sustainability section translated release drafts, even unfinished ones
February Figures financial statements and notes translated supply the final figures
February to March Revision and two correction rounds reviewed full version set the review window, name one approver
March to April Typesetting, galley proofs, online version version ready for print and publication provide the layout and access to it

Further languages build on the approved English version, usually a week behind. With French and Spanish that is straightforward. For Asian languages, allow more room for typesetting, because line breaks and character widths change the layout. The order of the languages follows your publication plan rather than the word count.

Embargo: the team is named before the first file

Until publication the content is price-sensitive and sits under embargo. Three things follow for the way the project is organised, and all three are settled before the first document moves.

The group of people

Named individually: project management, translation, revision, typesetting. Anyone joining later needs their own clearance. That is why the team is sized for the peak in March rather than the average.

How files travel

One channel, not three. Whether through tolingo connect or a secure transfer folder, what counts is that no version goes out as an attachment to a mailing list.

The deletion plan

What gets deleted after publication and what stays in the translation memory for next season is put in writing beforehand, not debated in April.

tolingo is certified to ISO 17100, ISO 18587, ISO 9001 and ISO 27001. For this part, the relevant elements of the information security standard are access rights, the named group and documented retention periods. How that works in practice is set out under quality and certifications. The non-disclosure agreement comes at the start, not between two deliveries.

Correction rounds: two is the planning figure

One correction round covers the return of the comments, the edit, the check on the edit and the new version. For an English report version that usually takes three to five working days. Two rounds are in the plan. The third and fourth almost always come from the same source: comments that contradict each other.

What makes the difference is how the review is organised rather than how thorough it is. Three rules are enough:

  • One window for everyone. Investor relations, corporate communications, financial reporting and legal comment in the same period rather than in sequence.
  • One person to consolidate. Contradictions are resolved before the comments come back. Two opposing comments on the same passage will produce another round.
  • One format. Comments in the document or in one list, not spread across email, chat and phone calls.

A third round can be planned for if you expect it. It only gets expensive when it turns up unannounced in March and pushes the galley proof correction back.

One terminology for two parts of the report

Internally, the management report and the sustainability section are usually written by different departments. Translation is where they first meet, and that is where it becomes obvious that the same thing has two names. The usual candidates are segment names, definitions of performance measures, references to periods, and the naming of sites or legal entities.

With ESRS data points there is a further complication: the English and the local version of the framework are both in circulation. If the management report uses one term and the sustainability section another, analysts read that as two different things. This is not a translation question. It is a decision for the company, and translation only makes it visible.

The process for it is short. Last year's report yields a list of the recurring terms, we mark the twenty to thirty contested ones, and a 45-minute meeting settles them. The result is maintained in terminology management and then governs press releases, presentations and your corporate communications as well.

For notes with a high repetition rate, post-editing to ISO 18587 can be the right treatment; for the foreword and the strategy section, specialist translation is. That choice is made chapter by chapter and it affects the budget, see prices.

Questions about running the project

Who is in the embargo group on the supplier side?

Project management, the translators for each language, the reviser and, once typesetting starts, the proofreader. The group is named and documented at the start of the project. It can be widened, but that takes time, because each addition is cleared and logged.

What happens to the files after publication?

That follows the deletion plan you agree. The usual arrangement is that working files are deleted while the translation memory and the term list stay, because they reduce the effort next year.

Can the management report and the sustainability section go to different teams?

Yes, and with a large volume that makes sense. It requires the shared term list and a revision that covers both parts. Without that bracket you get exactly the discrepancies that surface in spring.

What if the audit of the sustainability section runs late?

Then that part comes out of the shared round and follows separately. What matters is that the term list is already settled by then, otherwise the discussion moves into the tightest phase of the project.

Terms

Annual report
A company's yearly report: the narrative section, the management report, the financial statements with notes and, where required, the sustainability section.
Correction round
One full pass of commenting, editing, checking the edit and issuing a new version. For a report version the planning figure is three to five working days.
Embargo
The period in which price-sensitive content stays with a limited group of people. It governs staffing, file handling and retention.
ISO 27001
The standard for information security management systems. In a report project it comes down to access rights, the named group and documented retention periods.

Capacity for the 2027 season

We are holding capacity for the 2027 reporting season. The backward plan, the document types and the booking form are on our annual report translation page. Last year's report is enough for a first assessment.

The team answers questions about the process under contact.

Related

Last updated: 22 September 2026. Editorial team: tolingo GmbH, Hamburg.

Contents

Your contact

Philipp Walzok

We reply within ~10 minutes (within business hours).

service@tolingo.com
0800 55 133 00

To settle before the November meeting

  • publication date and target languages
  • approver for the English version
  • review group and review window
  • who sits inside the embargo
  • deletion plan for after publication